Question 476

A project manager has been assigned to a project and receives the project charter from the project management office (PMO). The document is very clear about customer requests. During Project Scope Management some requirements seem to be different from the ones specified within the project charter.

What should the project manager do?

    Correct Answer: C

    When there are differences or changes in project requirements that deviate from the project charter, it is essential to follow the change control process. The project manager should document the changes in a configuration management plan and submit them to the Change Control Board (CCB) for review and approval. This ensures that changes are properly evaluated and their impact on the project scope, schedule, and cost are assessed before any modifications are made. This approach aligns with standard project management practices for managing changes formally through a controlled process.

Discussion
AlekhyaTOption: B

Should analyse first why there is a difference in scope and project charter

WeslineoOption: B

My question is how do you know that these requests could endanger the schedule and cost of the project without first having details of the problem? The Sponsor should be our last point of call.So B should be correct

kevindebruyneOption: B

B first, then D Brainstorm first, then explain

Hung3102Option: B

B is answer

mrbottomwoodOption: C

**Configuration management** is the process of identifying, organizing, and controlling changes to the characteristics of a product or system. In this scenario, the project manager has identified that there are differences in the requirements compared to the ones specified in the project charter. To manage changes to the project scope, the project manager should follow the change control process. This involves documenting the changes in a change request and submitting it to the change control board (CCB) for review and approval.

[Removed]Option: C

Must change request first and then proceed to the next steps accordingly such as brainstorming etc

Bruce_LiuOption: C

Key is that this questions is for change management related, so choose C.

UppersquareCapitalOption: C

C. Register the changes in the configuration management plan and send it to the change control board (CCB). When there are differences or changes in project requirements that deviate from the project charter, it is important to follow the change control process. This involves documenting the changes in a configuration management plan and submitting them to the change control board (CCB) for review and approval. This ensures that changes are properly evaluated, and their impact on the project scope, schedule, and cost are assessed before any modifications are made. Option C aligns with the standard project management practice of formalizing and managing changes through a change control process.

Only12goOption: B

When there's a discrepancy between the requirements specified in the project charter and the ones emerging during Project Scope Management, it's crucial for the project manager to gain clarity. Option B suggests using a focus group and brainstorming sessions to gather more details about the project scope.

victory108Option: C

C. Register the changes in the configuration management plan and send it to the change control board (CCB)

kevzzzOption: B

Project scope management is a process that helps in determining and documenting the list of all the project goals, tasks, deliverables, deadlines, and budgets as a part of the planning process. In project management, it is common for a big project to have modifications along the way. With the scope in the project management defined right in the beginning, it becomes much easier for project teams to manage and make the required changes.

aqz_111Option: D

We should read the question very carefully. It said 'During project scope management' so the project is in execution stage, the scope has been baselined so B is not correct. the PM noted the requirements are not as the same as mentioned in project charter (High level). it intend to confuse you. He noted 'difference' means new requirements. when there is request, we have to perform integrated analysis on the change request impacts on schedule and cost and notified to the stakeholders. so D is the correct answer

kayyaly

how did you eliminate B? the project is in planning phase not execution, scope management has no processes in execution phase.

AlekhyaTOption: D

Changing to D as B mention focus groups which refer to SME. Cannot find the reason for the difference with SME. So possible solution as all remain void is D to inform the sponsor about the changes impact.

MIMINEDZOption: D

the question seeks our knowledge on the golden triangle, as soon as we touch one of the points the other two are impacted, so answer D

AstridN

The approach sounds good..

rajeshtkOption: B

B is the best answer.

TheAWSGuruOption: B

B is the answer .

PMPStudentOption: B

I think B seems better. Before reaching out to the sponsor, its best to understand and analyze the situation.