A project manager is appointed to manage an infrastructure project that spans across several countries, including different time zones within a subregion. It is likely that most of the project team members will never meet, but they will have to collaborate to ensure deliverables are met.

What should the project manager do to ensure good collaboration between the remote project team members?

    Correct Answer: D

    To ensure good collaboration between remote project team members, the project manager should plan a communication method and allow the team members to virtually interact. Effective communication is essential for remote teams, and establishing clear channels for interaction helps ensure that all members can collaborate efficiently despite the geographical and time zone differences.

Discussion
martinx84Option: D

Plan communication method