Question 84

Hal is the program manager for his organization. He would like your organization to provide his program with 4 tons of pea gravel for a construction project in his program. Hal send you a statement of work and an IFB. What document should you provide to Hal?

    Correct Answer: C

    When an organization receives a statement of work (SOW) and an Invitation for Bid (IFB) from a program manager, the appropriate document to provide in response is a bid. A bid is a formal proposal that outlines the price and terms for supplying the requested material or service. In this case, Hal requires 4 tons of pea gravel for a construction project, and providing a bid will detail your pricing and terms based on the specifications provided.

Discussion
tungdtOption: C

C is correct answer. Given that Hal has sent you a statement of work (SOW) and an Invitation for Bid (IFB), the document you should provide in response is a Bid. Explanation: Bid: In response to an IFB, you should submit a bid. This document will outline your proposed price and terms for supplying the 4 tons of pea gravel, based on the specifications and requirements detailed in the SOW and IFB.