CAPM Exam QuestionsBrowse all questions from this exam

CAPM Exam - Question 286


A project manager is reporting the project performance as 25 days worth of work completed against 13 days originally planned. What is the schedule variance (SV)?

Show Answer
Correct Answer: B

The schedule variance (SV) is calculated by subtracting the planned value (PV) from the earned value (EV). In this case, the earned value (EV) is 25 days worth of work completed, and the planned value (PV) is 13 days originally planned. Therefore, the schedule variance (SV) is 25 - 13, which equals 12.

Discussion

2 comments
Sign in to comment
shubu2276Option: B
Jan 26, 2024

SV=EV−PV SV=25−13 SV=12

ebbff63Option: B
May 24, 2024

Ans: B SV=EV−PV SV=25−13=12