Exam CAPM All QuestionsBrowse all questions from this exam
Question 286

A project manager is reporting the project performance as 25 days worth of work completed against 13 days originally planned. What is the schedule variance (SV)?

    Correct Answer: B

    The schedule variance (SV) is calculated by subtracting the planned value (PV) from the earned value (EV). In this case, the earned value (EV) is 25 days worth of work completed, and the planned value (PV) is 13 days originally planned. Therefore, the schedule variance (SV) is 25 - 13, which equals 12.

Discussion
shubu2276Option: B

SV=EV−PV SV=25−13 SV=12

ebbff63Option: B

Ans: B SV=EV−PV SV=25−13=12