PgMP Exam QuestionsBrowse all questions from this exam

PgMP Exam - Question 24


You are program manager for the HYH Program. Your program governance is requiring you to use earned value management to predict how closely your program is tracking to the cost and schedule baselines and to predict overall program performance. Which earned value management formula can you use to predict how much more will need to be invested in the program based on current program performance?

Show Answer
Correct Answer: D

To predict how much more will need to be invested in the program based on current program performance, the formula EAC-AC (Estimate at Completion minus Actual Cost) is used. This calculation provides the Estimate to Complete (ETC), indicating the additional funds required to complete the project from the current point forward, considering any deviations from the original cost performance.

Discussion

1 comment
Sign in to comment
tungdtOption: D
Jun 30, 2024

D is correct