Question 13

You are the program manager for the SRQ Program. You have rejected several change requests for the program scope. What must you do with the rejected change requests?

    Correct Answer: C

    As the program manager, it is essential to communicate the status of all change requests to the stakeholders and properly document the outcomes. This ensures transparency and maintains accurate records for future reference. The correct procedure involves updating the change register, which logs all change requests and their statuses, ensuring that any actions taken are properly recorded and communicated to the relevant parties for program oversight and governance.

Discussion
SergeyKOption: C

C, but Change Log should be used instead of Change Register

tungdtOption: C

Definitely, C is right answer but I'm confused between change register and chang log.

FareedKamranOption: C

It must be Change log, not the change register.

Abdel36

HUGE: YESSS

HugeOption: C

I don't know how much PMI interchanges log vs register, but there is no such thing as a change register in the Standard for Program Management, it is a Change Log.

ReevesT

This is absolutely correct. There is no Change Register, it is a Change Log. One would think it doesn't matter except that there are questions where wrong options are given as Change Register No where in the PMBOK is there a the word Change Register. Somebody please change this question.