Question 224

During daily team standup meetings, team members constantly ask about which tasks they should focus on first.

How should the project manager ensure the team is fully productive?

    Correct Answer: D

    To ensure that the team is fully productive and aware of task priorities, the project manager should work with the product owner to ensure the project backlog is prioritized. This way, the tasks that require immediate attention are clearly defined, reducing confusion about task priorities during standup meetings.

Discussion
ArulanandamOption: D

How is that the Product Manager is asked to do prioritization of Project Backlog? Product owner can only prioritize Product Backlog....! Project backlog should be reviewed and prioritized by the team.

alltakenOption: D

"team members constantly ask about which tasks they should focus on first", this implies there is no clarity and tasks are not properly communicated/prioritized.

sddharthaOption: C

question doesn't mention the backlog

madusankagdOption: D

D. Work with the product owner to ensure the project backlog is prioritized.

Lucky_CindyOption: D

D. Work with the product owner to ensure the project backlog is prioritized.

AsakthiOption: D

D. Work with the product owner to ensure the project backlog is prioritized.

victory108Option: D

D. Work with the product owner to ensure the project backlog is prioritized

RagazzoAlexOption: D

set priority should be in coordination with the product owner or manager