Question 101

Holly is the program manager for her program. She is creating with her team a plan that will address how the program team will achieve program goals based on who the program will need to interact with in the program. This plan should define all of the people, groups, and other entities the program needs to interact with in order to move the program forward. On what plan is Holly working?

    Correct Answer: A

    Holly is working on the stakeholder management plan. This plan defines all the people, groups, and other entities that the program needs to interact with in order to achieve its goals. It encompasses identifying and analyzing stakeholder needs and expectations and planning how to engage and communicate with them effectively.

Discussion
snow5Option: D

It is D simply cuz the question is asking about interact

tsangcklOption: B

Sorry it is B. communication management plan, there have no stakeholder management plan, only engagement plan

tungdtOption: B

B is correct

happykaurOption: B

There is no Stakeholder Management or Interface Mgmt Plan in PGMPBOK

tsangcklOption: A

I pick A