Question 1096

In a global project, the project manager has to plan and manage communication between the team members and stakeholders in order to ensure the project will remain on track and achieve its goals.

What should the project manager do?

    Correct Answer: A

    In a global project, it is crucial for the project manager to consider cultural differences among stakeholders. This awareness allows for the creation of a communication plan that is sensitive to diverse backgrounds, which is essential for maintaining effective communication and collaboration. By understanding and respecting cultural differences, the project manager can ensure that all team members feel valued and understood, thereby increasing the likelihood of the project remaining on track and achieving its goals.

Discussion
AzharmakOption: A

By focusing on cultural differences, the project manager can create a communication plan that respects and incorporates the diverse backgrounds of all team members and stakeholders, thereby enhancing the likelihood of the project remaining on track and achieving its goals.