Exam PMP All QuestionsBrowse all questions from this exam
Question 202

A company is working on a project to develop an integration of their existing systems. There are known issues in production.

What should the project manager do?

    Correct Answer: A

    When there are known issues in production during a project to integrate existing systems, the primary responsibility of a project manager is to address these issues directly. This involves identifying and removing any impediments that are causing the issues and mitigating associated risks to ensure the project can progress smoothly. Therefore, the most appropriate action for the project manager is to identify and remove impediments and mitigate the risks.

Discussion
KennethTangOption: A

Why A? "Identify and remove impediments" is correct, but not mitigate the risks, It already became an issue now.

segatarasov

exactly!

DRohanOption: D

in question it is stated as an issue, so it is not a risk, option A gets eliminated there. Option D mentions reviewing the quality process which is better option

Sumit182

Question says" Known issues". Known issues are nothing but " Risks". An unknown or unidentified risks if it occurs is called an issue. Moreover there are production issues, that may not be necessarily quality issues. Content of the question nowhere states that there is issue with quality per se. So option A is the best fit...

YOLO28Option: A

According to Chat GPT: As the company is working on a project to develop an integration of their existing systems and there are known issues in production, the project manager should focus on identifying and removing impediments and mitigating risks. Therefore, option A is the most appropriate choice. While ensuring the product owner reviews requirements with the team (option B), including acceptance criteria in the definition of done (DoD) (option C), and reviewing the quality control processes and procedures (option D) are all important tasks, they are not the most critical tasks in this scenario. The priority is to address the known issues in production and ensure that the project moves forward smoothly, without any roadblocks or impediments.

OruMaryOption: D

D - this is a production issue and not an impediment to development. Hence, the need to review the quality control and assurance.

estimaterOption: A

since the issues are known , next step is to remove the impediments

AsakthiOption: A

A. Identify and remove impediments and mitigate the risks.

victory108Option: A

A. Identify and remove impediments and mitigate the risks

SteAle

Changed my mind, I would go with D. How are some impediments related to the issues in production?! I don't see any connection.

SteAleOption: A

If we assume that the question talks about some issues in the production environment of the existing systems that need to be integrated as part of the ongoing project's scope, that yes, from a project perspective, it is a risk not an issue.

MattAnyaOption: A

Option A is correct. As the issues need to be identified, removed and the issues mitigated

[Removed]Option: C

Is it the PM's job to identify impediments? The answer should be "C" because there is a quality issue identified so the PM should provide oversight to the quality processes.

TrytrioOption: D

I would pled for D...any other opinion?

RagazzoAlexOption: D

I tend to D, the Question did not mention anything about risks. although if there are known issues in production, that means that the QA process is flaw.

Sumit182

Known issues in production could pertain to Schedule, cost or procurement . Not necessarily quality unless stated otherwise in the content of the question.