PMP Exam - Question 1250


A human resources (HR) cost report was disclosed, by error, to all members of the project team. This situation generated a conflict between the team members about differences in their salaries.

What should the project manager have done to avoid this situation?

Show Answer
Correct Answer:

Discussion

3 comments
Sign in to comment
victory108Option: D
Sep 29, 2024

D. Validated the information and the appropriate recipients per the communications management plan

JordarluOption: C
Feb 19, 2025

the project manager wouldn't typically have control over emails sent by the HR department. I will vote for C

arthigafOption: C
May 3, 2025

C is correct answer