PMP Exam - Question 2


A team has just adopted an agile approach. During daily standup meetings, the team expressed concerns about task delays. The project leader worked with the product owner to get clarity on the features. The project leader asked the team to fast-track all product features to ensure delivery. Sprints are being completed but with either fewer features or low quality.

What should the project leader have done to ensure success?

Show Answer
Correct Answer: D

In an agile approach, success is often achieved by empowering the team to improve their processes, tools, and interactions to be more effective in delivery and removing impediments. Empowering the team fosters autonomy, accountability, and continuous improvement. The project leader should enable the team to address and resolve issues independently, which is consistent with the principles of agile methodologies that promote self-organizing and cross-functional teams.

Discussion

56 comments
Sign in to comment
ronanncirl
Oct 11, 2022

In agile PMs need to be servant leaders... this means empowering the teams to resolve themselves - Answer D is correct

AlonsochavesOption: D
Apr 2, 2024

Can get easily confused with B, but in agile the team must find a solution themselves.

Pakawat
Sep 9, 2022

It should be : B

PlangeOption: D
Nov 17, 2022

Answer D

Ganzee
Dec 15, 2022

D. Empowered the team to improve their processes, tools, and interactions to be more effective in delivery and removing impediments

AlluJuju
Feb 1, 2023

B could be a good answer, because its a new Agile team, so the team is not well versed, so directing the team is a good option.

rajeshtk
Apr 4, 2023

Agile Manifesto says individual and interaction over processes and tool. The best answer would be "B".

Caesar88Option: D
Mar 25, 2024

In agile PMs need to be servant leaders... this means empowering the teams to resolve themselves - Answer D is correct

mahafidoOption: D
Nov 29, 2024

The PM has to empower the team and assist them to adopt agile methodologies and midset

YSO34
Sep 5, 2022

@all : are you sure about the answer ? I Saw answer A on other platforms

rajeshtk
Sep 14, 2022

The best approach to solve the impediments in the same sprint rather than carry over to the next sprint

NatieRouge
Mar 8, 2023

Which one did turn out to be the correct one?

Arulanandam
Dec 23, 2022

Vote D

pavan555manjunath
Jan 11, 2023

Vote D

PMPStudentOption: D
Jan 20, 2023

D is correct

karimSaferganyOption: D
Jan 22, 2023

because this issue for the project manager needs to Be Crashing the duration by increasing manpower and tools and equipment to reach the owner requirement at the time and quality requirement.

Midos_AhbOption: D
Feb 28, 2023

Answer D is Correct

Rena1352Option: D
Mar 15, 2023

D is correct

Danielle1920Option: D
Mar 19, 2023

voted for D

Anna12675Option: D
Apr 19, 2023

voted D

BenPappoeOption: D
Apr 24, 2023

Voted D

_MMS_Option: D
Apr 26, 2023

To make progress, interactions btw TMs and better understanding of P& T will help

Whydotty
May 2, 2023

i feel A is correct, impediment needs to be identified and registered so corrective measures can be planned and put in place.

SSRM
May 2, 2023

I vote A

MakinskimOption: D
May 7, 2023

I vote D

victory108Option: D
May 7, 2023

D. Empowered the team to improve their processes, tools, and interactions to be more effective in delivery and removing impediments

sultanalsanieOption: D
May 10, 2023

I vote D

Mo_baby
May 15, 2023

d is correct

Bimsoft
Jun 2, 2023

We should empower, D

Acumen88
Jun 7, 2023

The answer should be B. The agile environment focuses on people rather than processes and tools, so empowering the team on processes and tools defeats the agile manifestoes. Option B seems most suitable as it discusses the empowerment of the project team to remove impediments and deliver timely.

Fela80Option: D
Jun 12, 2023

The project leader is meant to empower the team member to remove impediments

QUSAROption: D
Jun 25, 2023

D is the right answer

Mbolatiana
Jul 17, 2023

always empower the team so D

Aish_Option: D
Aug 1, 2023

As a servant leader, you are not supposed to stay away from the situation, by "asking team to do" or "direct" the team. Servant leaders should support the team, empower them and remove impediments.

Mahi_02021988
Aug 4, 2023

Answer is D

elshaikha
Aug 17, 2023

the team has just adopted agile practices, means they are new to agile. the PM should be directive until the team settles in and become self organized. my answer is B

harryjmu
Aug 29, 2023

Answer is D empowering is part of agile

Roody_28Option: D
Sep 5, 2023

B is wrong because servant leader doesn't direct , rather empower

Ravi4frenchOption: B
Oct 4, 2023

B. Directed teams to possible solutions that help in removing the impediments and contribute to a timely delivery

xcjxcjOption: D
Jan 3, 2024

should be D. if B is correct, then fast-track would be the decision and the result is as of now.

BuviDOption: D
Jan 4, 2024

D. Empowered the team to improve their processes, tools, and interactions to be more effective in delivery and removing impediments

DMHR
Jan 17, 2024

answer - D

Aditech
Apr 11, 2024

D The project leader should have focused on addressing the root cause of the task delays rather than rushing to fast-track features. They could have facilitated discussions with the team to identify and resolve any blockers or misunderstandings. Additionally, they should have encouraged collaboration between the team and the product owner to ensure clear understanding of priorities and expectations, and to adjust the sprint scope accordingly to maintain quality. Adigun.

Yaaz1
Jun 13, 2024

In agile PMs need to be servant leaders. D is the right answer

Taha1981
Sep 16, 2024

Answer D

Pragati06
Sep 18, 2024

Answer is D as in Agile team is empowered to resolve issue themselves

MaiB
Sep 26, 2024

Answer is D In Agile the Team is always empowered to work autonomously and therefore should solve issues as they arise.

crypto_dreams_medellin
Nov 7, 2024

The issue is the lead is just fast tracking the work and not addressing the feed back from the rest of the team. For all we know, he is over looking gaps, scheduling too much work, etc. involve the team and use tools better processes, and root cause the issues before they become issues.

MalikSaabOption: D
Dec 3, 2024

In scrum, PM's role is to empower the team and remove impdeiments

ttkong168Option: D
Dec 9, 2024

Project team should be empowered in Agile env.

FauziYusminOption: D
Jan 1, 2025

To ensure the success of the agile project, the project leader should have focused on proper backlog grooming, clear sprint goals, prioritization of features based on value, maintaining quality standards, and fostering team collaboration. By avoiding the temptation to fast-track features and instead emphasizing incremental delivery, the team would have been able to deliver high-quality, valuable product features while addressing delays and concerns in a more sustainable way.

TerryV01Option: D
Feb 6, 2025

answer D as the PM should empower the team to resolve issues in the projects

engaminOption: D
Feb 8, 2025

D answer D is corect

Princessviv96Option: D
Mar 28, 2025

The answer is D. The main concern as regards any project is timely delivery and quality. It is important that as a project manager you are able to implement procedures that ensure quality and in this case the project leader needs to empower his team.

JAQMOption: D
Apr 10, 2025

Complementaria la repuesta de empoderar al equipo y revisar los retrasos que indica el equipo sobre los sprint con el fin de generar prioridades con el equipo para alcanzar la meta propuesta sin bajar la calidad de lo que se debe entregar.

HubertPOption: D
Apr 15, 2025

D is my answer

SaadalfehriOption: D
Apr 17, 2025

the answer is D, Empowerment is the power of agile method

ChagosOption: D
Apr 30, 2025

servant leadership