PMP Exam QuestionsBrowse all questions from this exam

PMP Exam - Question 64


A project manager is leading a multiyear project that involves internal and external stakeholders. As the project manager begins to gather requirements, additional business stakeholders express interest in being involved.

Which three actions should the project manager take to ensure proper stakeholder involvement? (Choose three.)

Show Answer
Correct Answer: ABE

To ensure proper stakeholder involvement, the project manager should prioritize stakeholders based on the project phase and need to ensure that those most relevant to the current stage are given appropriate attention. Performing a stakeholder assessment aligns with the project objectives, helping to understand and address the needs and expectations of each stakeholder. Developing a stakeholder impact/influence matrix will help determine the appropriate level of engagement for each stakeholder based on their influence and impact on the project, ensuring effective allocation of resources and communication efforts.

Discussion

17 comments
Sign in to comment
leo_goldOptions: ABD
Dec 15, 2022

Be make sense more than C! remember not all stakeholders are internal (Part of your organization).

Ab5434
Dec 17, 2022

Classify and rank stakeholders based on their positions in the organizatio, Doesn't this mean power in the organization?!

leo_gold
Dec 22, 2022

I meant ABE - I'm staying with the suggested answers.

BuviDOptions: BCE
Jan 5, 2024

B. Perform a stakeholder assessment to align with the project objectives E. Develop a stakeholder impact/influence matrix to determine the level of engagement C. Classify and rank stakeholders based on their positions in the organization

crishnamohanOptions: BCE
Nov 4, 2022

B, C, E makes sense to me

lxplxplxpOptions: ACE
Nov 16, 2022

B stakeholder assessment to align with the project objectives???????

arnibert
Nov 24, 2022

Easiest way to get the correct answer here was exclusion of C and D :-)

hary61Options: ABE
Jan 6, 2023

ABE ...recheck question...only option is ABE

lilylam08Options: ABE
Apr 8, 2023

C - position do not have direct relation with impact D - obviously “same” handling is incorrect

akashushi007Options: ABE
May 17, 2024

A B E..

kakahoanghuyOptions: ABE
Jul 14, 2024

Incorrect Options: C. Classify and rank stakeholders based on their positions in the organization: While understanding stakeholders' positions can be useful, ranking them solely based on their organizational positions might not reflect their actual influence or impact on the project. D. Include all stakeholders in the stakeholder engagement plan and provide the same level of communication: This is not practical or efficient. Different stakeholders have different levels of interest and influence, and they require different levels of communication and engagement. Providing the same level of communication to all stakeholders can lead to unnecessary overload and inefficiencies.

novantunoOptions: ACE
Dec 2, 2022

B seems right but I have some doubt in the logical sense.

GanzeeOptions: ADE
Dec 15, 2022

A, D, E

gspaceOptions: ABE
Feb 26, 2023

C would not be a good candidate here because the whole idea of classifying and ranking stakeholder is to access impact and influence so E supersedes C because of the end goal.

JYKL88Options: ABE
May 5, 2023

wll go with ABE. CD dont sits well with me

victory108Options: ABE
May 21, 2023

A. Prioritize stakeholders based on the project phase and need B. Perform a stakeholder assessment to align with the project objectives E. Develop a stakeholder impact/influence matrix to determine the level of engagement

smartrammyOptions: ABE
Jul 5, 2023

A. Prioritize stakeholders based on the project phase and need B. Perform a stakeholder assessment to align with the project objectives E. Develop a stakeholder impact/influence matrix to determine the level of engagement

Asakthi
Aug 9, 2023

A, b, d

IfyyOptions: ABE
Sep 28, 2023

I go for ABE too

mesacgonOptions: ABE
Oct 23, 2023

De acuerdo con ABE