In the middle of an iteration, the product owner tells the agile team that the government has updated legal requirements. This will result in some changes in the product definition.
How should the project manager handle this situation?
In the middle of an iteration, the product owner tells the agile team that the government has updated legal requirements. This will result in some changes in the product definition.
How should the project manager handle this situation?
In the middle of an iteration, it's crucial to reassess the iteration backlog when there are changes in product definition due to updated legal requirements. This ensures that the team addresses these changes immediately and maintains compliance. By reviewing the iteration backlog, the agile team, including the product owner, can reprioritize tasks to align with the new legal requirements and ensure that the project remains on track.
Review the iteration backlog because the product definition has changed and needs to be reassessed before continuing the project. This option ensures that the team addresses the changes immediately and integrates them into the current iteration in a way that maintains compliance and aligns with the updated product definition. It involves the product owner and the team reassessing and reprioritizing the iteration backlog, ensuring that the project remains on track and meets the necessary legal requirements.