PMP Exam QuestionsBrowse all questions from this exam

PMP Exam - Question 63


A key project stakeholder has started to escalate all issues and main requirements to the project sponsor. The project manager is concerned about the team not receiving direct communications from this stakeholder.

Which two actions should the project manager take to improve the relationship with the stakeholder? (Choose two.)

Show Answer
Correct Answer: B,E

To improve the relationship with the stakeholder, it is crucial to promote an environment where communication is open and transparent. This enables the team to communicate directly with stakeholders, addressing any concerns promptly. Additionally, scheduling regular meetings with the key stakeholder provides a structured opportunity to update them on the project's progress and to receive their feedback, further strengthening the relationship and ensuring alignment with project goals.

Discussion

15 comments
Sign in to comment
zul_nOptions: BE
Dec 10, 2022

A. Provide training to the team on emotional intelligence and status reporting techniques - PM delivers status report, not the team members B. Promote an adaptive and transparent environment where the team can easily communicate with the stakeholders - make sense building relationship with the stakeholders C. Share weekly status reports with detailed information about the project and team performance - won't help building relationsahip with the stakeholders D. Submit performance reports and task assignments to keep the stakeholder informed - won't help building relationsahip with the stakeholders E. Schedule regular meetings with the key stakeholder to provide updates and receive feedback - make sense building relationship with the stakeholders

longgeOptions: BE
Oct 12, 2022

focus on communication

rajeshtkOptions: AB
Oct 10, 2022

Isn't it A&B the correct answer?

PMPStudentOptions: BE
Dec 13, 2022

B and E are correct

GanzeeOptions: BE
Dec 15, 2022

B AND E

viethunggenOptions: BE
Dec 17, 2022

BE is correct

sanjeevjhaOptions: BE
Jan 13, 2023

B & E is correct option

victory108Options: BE
May 21, 2023

B. Promote an adaptive and transparent environment where the team can easily communicate with the stakeholders E. Schedule regular meetings with the key stakeholder to provide updates and receive feedback

Red_Apple1Options: BE
May 25, 2023

i thick B & E

AH1007Options: BE
Jun 4, 2023

B and E are suitable for this situation.

MuntadherOptions: BE
Jul 22, 2023

most applicable choice B and E

AsakthiOptions: BE
Aug 9, 2023

B and E

stujamOptions: BE
Aug 10, 2023

B & E.

BuviDOptions: CE
Jan 5, 2024

E. Schedule regular meetings with the key stakeholder to provide updates and receive feedback and C

ParamakOptions: BE
Jul 18, 2024

Promote a transparent environment for the team and schedule regular meetings with stakeholder and get their feedback. Both promotes Agile methodology.