Exam PMP All QuestionsBrowse all questions from this exam
Question 63

A key project stakeholder has started to escalate all issues and main requirements to the project sponsor. The project manager is concerned about the team not receiving direct communications from this stakeholder.

Which two actions should the project manager take to improve the relationship with the stakeholder? (Choose two.)

    Correct Answer: B, E

    To improve the relationship with the stakeholder, it is crucial to promote an environment where communication is open and transparent. This enables the team to communicate directly with stakeholders, addressing any concerns promptly. Additionally, scheduling regular meetings with the key stakeholder provides a structured opportunity to update them on the project's progress and to receive their feedback, further strengthening the relationship and ensuring alignment with project goals.

Discussion
zul_nOptions: BE

A. Provide training to the team on emotional intelligence and status reporting techniques - PM delivers status report, not the team members B. Promote an adaptive and transparent environment where the team can easily communicate with the stakeholders - make sense building relationship with the stakeholders C. Share weekly status reports with detailed information about the project and team performance - won't help building relationsahip with the stakeholders D. Submit performance reports and task assignments to keep the stakeholder informed - won't help building relationsahip with the stakeholders E. Schedule regular meetings with the key stakeholder to provide updates and receive feedback - make sense building relationship with the stakeholders

longgeOptions: BE

focus on communication

ParamakOptions: BE

Promote a transparent environment for the team and schedule regular meetings with stakeholder and get their feedback. Both promotes Agile methodology.

BuviDOptions: CE

E. Schedule regular meetings with the key stakeholder to provide updates and receive feedback and C

stujamOptions: BE

B & E.

AsakthiOptions: BE

B and E

MuntadherOptions: BE

most applicable choice B and E

AH1007Options: BE

B and E are suitable for this situation.

Red_Apple1Options: BE

i thick B & E

victory108Options: BE

B. Promote an adaptive and transparent environment where the team can easily communicate with the stakeholders E. Schedule regular meetings with the key stakeholder to provide updates and receive feedback

sanjeevjhaOptions: BE

B & E is correct option

viethunggenOptions: BE

BE is correct

GanzeeOptions: BE

B AND E

PMPStudentOptions: BE

B and E are correct

rajeshtkOptions: AB

Isn't it A&B the correct answer?