Question 18

Mike is the program manager of the NHQ Program. Mike and a vendor are in disagreement over the deliverable the vendor has created for Mike's program. Mike does not believe the vendor has correctly created the deliverable, while the vendor is adamant that his company has indeed completed the contract. Both parties have documented their stance in the debate.

This is an example of what?

    Correct Answer: D

    A claim is a demand or assertion by one party to try to obtain an adjustment or interpretation of contract terms or to seek payment for certain damages. In this situation, the dispute over whether or not the vendor has met the contract deliverables fits the definition of a claim.

Discussion
FareedKamranOption: B

its an issue and need to be logged in issue log.

KukushaOption: B

It looks issue than claim

SergeyKOption: D

It's a Claim. D is the correct answer

tungdtOption: B

this is a issue and need to log in issue log. B is anwser.