Exam PMP All QuestionsBrowse all questions from this exam
Question 177

A company has started developing a new product. During execution the project team notices that another competitor has launched a product with very similar functionalities and a cheaper market price.

What should have been done differently to avoid this scenario?

    Correct Answer: D

    An iterative life cycle approach should have been adopted. This approach involves shorter development cycles with frequent reassessments and adjustments. It allows a project team to respond rapidly to changes in market conditions and competitors, thereby minimizing the risk of developing a product that is already outperformed or outpriced by competitors. By frequently iterating and reassessing, the team could have detected the competitor's product early and adjusted their strategy accordingly.

Discussion
AbbasTakiOption: A

A. A minimum viable product (MVP) should have been released to get feedback from the market.

KhoiCXOption: D

The problem here was not the feedback or requirements. It is the pace of the product. So I vote D.

Lucky_CindyOption: A

A, MVP to get feedback fast

AsakthiOption: A

A. A minimum viable product (MVP) should have been released to get feedback from the market

victory108Option: A

A. A minimum viable product (MVP) should have been released to get feedback from the market