PgMP Exam - Question 99


Which one of the following is not an output of the direct and manage program execution process?

Show Answer
Correct Answer: D

The direct and manage program execution process involves executing the program activities, producing work results, managing the budget, and handling change requests. A request to terminate the program is not typically an output of this process as it usually arises from risk management or decision-making processes related to program closure.

Discussion

1 comment
Sign in to comment
tungdtOption: D
Jul 5, 2024

D is correct. A request to terminate the program is not an output of the Direct and Manage Program Execution process. This process focuses on executing the program activities according to the program management plan, producing results of program work, managing the program budget, and handling change requests as necessary. Termination requests typically arise from other circumstances or processes, such as risk management or decision-making processes related to program closure.