Question 533

A team is currently working on a mobile app solution. During sprint execution, one of the developers requires clarification about the acceptance criteria for a particular task.

What should the project manager do to obtain the information required by the developer?

    Correct Answer: D

    The appropriate course of action for the project manager in this situation is to work with the product owner to clarify the requirement. The product owner is responsible for defining and prioritizing the product backlog, which includes acceptance criteria for tasks. They serve as the main point of contact between the development team and the stakeholders, ensuring that the team's work aligns with the client's needs and expectations. Therefore, collaborating with the product owner is the most direct and efficient way to obtain the necessary information to clarify the task for the developer.

Discussion
DavidTriOption: D

PO is responsibility for system requirement

victory108Option: D

D. Work with the product owner to clarify the requirement

SteAleOption: D

PO should help in clarifying the requirement

AstridNOption: D

I'm ok w/ D