Exam PgMP All QuestionsBrowse all questions from this exam
Question 5

You are the program manager of the NHQ Program. You are working with your program team to ensure that the work in the program is done accurately and according to scope. You are also reviewing the team inspection process that will need to be done to ensure that the work is being done according to the scope. If the work is found to be defective it will need to be corrected before the program customers can inspect the work. What process are you completing to ensure that the work is done accordingly to scope?

    Correct Answer: A

    The process being described involves inspecting the work to ensure it's done correctly and according to scope, and then correcting any defects found before presenting it to the customers. This is characteristic of quality control, which focuses on identifying defects in the actual products or results of the project and addressing them. Quality assurance, on the other hand, would involve the processes and activities put in place to ensure that quality requirements will be met, focusing on preventing defects in the processes used to create the deliverables. Therefore, the correct answer is quality control.

Discussion
LuanNDOption: A

totally agree with A

tungdtOption: A

Answer is A

Ahsan_tirmiziOption: C

yes Quality assurance

mfshabanaOption: C

Quality assurance involves processes and activities that ensure the project is being executed and the deliverables are being produced according to the planned scope, standards, and requirements. It includes activities such as process audits, reviews, and inspections to identify and correct any defects or issues in the work before it is presented to the program customers. This helps in preventing defects and ensuring the overall quality of the project.