PMP Exam - Question 1013


A project is being planned to deliver a proof of concept to evaluate technology compatibilities. The business and project stakeholders are having difficulty agreeing on what should be included in the final product.

What should the project manager do?

Show Answer
Correct Answer: D

The project manager should determine the root cause of the stakeholders' inability to define the project scope. Identifying the underlying issues will help facilitate a more focused and effective resolution, ensuring that all stakeholders' concerns are properly addressed. This approach helps in achieving clarity and agreement on what should be included in the final product.

Discussion

2 comments
Sign in to comment
517f9daOption: D
May 14, 2024

D. Determine the root cause of their inability to determine the project scope Determining the root cause of their inability to define the project scope helps identify the underlying issues, facilitating a more focused and effective resolution, and ensuring that all stakeholders' concerns are addressed properly.

martinx84Option: D
Jul 2, 2024

Determine root cause