PMP Exam QuestionsBrowse all questions from this exam

PMP Exam - Question 601


A geographically distributed project team has development issues between the collocated and virtual teams causing productivity to decrease.

What should the project manager do to address this issue?

Show Answer
Correct Answer: B

For addressing development issues and improving productivity within a geographically distributed project team, developing protocols for resolving conflicts between team members is crucial. Conflict resolution protocols can provide a structured approach to resolving inherent differences and misunderstandings that may arise between collocated and virtual teams, thereby enhancing productivity and teamwork. This method addresses the root cause of productivity issues rather than just providing a temporary fix.

Discussion

6 comments
Sign in to comment
LuanNDOption: B
Apr 9, 2023

Absolutely. PMKBook 6, page 370 mentioned

[Removed]
May 2, 2023

yes. best answer so far and the best reference too

adviseleeOption: B
May 12, 2023

I understand A,C,D can't be the answer. But, how can the development issue be categorized into conflict? It's hard to understand

leggoteamOption: D
Jul 8, 2023

Finding ways to conduct Face to face interaction is most ideal for building rapport

victory108Option: D
Sep 23, 2023

D. Set up face-to-face meetings with project team members

22d5af5Option: B
Jan 9, 2024

Selected Answer: B

tonybuivannghiaOption: D
Jul 19, 2024

This is the issue, so we need to do a assessment before finding a solution to solve the problems.