The steering committee has asked a project manager experienced in agile to provide an indication of the time remaining on a medium-sized project.
What tools can be used to provide this information?
The steering committee has asked a project manager experienced in agile to provide an indication of the time remaining on a medium-sized project.
What tools can be used to provide this information?
A release burndown chart is commonly used in agile project management to provide an indication of the time remaining in a project. It visually shows the progress of completed and remaining work and helps project managers forecast if the project is on track to be completed within the remaining time.
C .. anyone?