PMP Exam QuestionsBrowse all questions from this exam

PMP Exam - Question 26


A project manager works in a hierarchical organization. The project team members are used to being told what to do, and the performance reviews include the percentage of completion of the allocated tasks. After a conversation with the sponsor, the project manager realizes that they need to reassign a couple of tasks to meet the next milestone. This change can be perceived as poor performance by the current assignees.

What should the project manager do?

Show Answer
Correct Answer: D

The project manager should organize a team meeting to inform team members about a change in direction and work with them to change the task allocation. This approach maintains transparency, encourages team collaboration, and mitigates any perceptions of poor performance by involving everyone in the decision-making process. It also helps to uphold the hierarchical structure while addressing the necessary changes in a respectful and inclusive manner.

Discussion

12 comments
Sign in to comment
gspaceOption: A
Feb 25, 2023

Option A might be worth exploring here. In the question, it says the team members are used to being told what to do + they are under a hierarchical system. Sounds like a plan driven environment.

GanzeeOption: D
Dec 15, 2022

D. Organize a team meeting to inform team members about a change in direction and work with them to change the task allocation

SteAleOption: D
Jun 27, 2023

D. Organize a team meeting to inform team members about a change in direction and work with them to change the task allocation

MuntadherOption: D
Jul 22, 2023

D most fit

Hungdv
Mar 16, 2023

A or D?

Hung1
Apr 18, 2023

D is answer

Anna12675Option: A
Apr 20, 2023

a or d

BenPappoeOption: D
Apr 25, 2023

Voted D

victory108Option: D
May 7, 2023

D. Organize a team meeting to inform team members about a change in direction and work with them to change the task allocation

GabMontereyOption: D
Dec 2, 2023

D is best asnwer

BuviDOption: D
Jan 4, 2024

D. Organize a team meeting to inform team members about a change in direction and work with them to change the task allocation

hihemant1509Option: D
Jan 19, 2024

D is the best answer

kazu91Option: D
Jul 17, 2024

This change can be perceived as poor performance by the current assignees. => Current process is facing problem. We need to change, firstly is Task Allocation, and asking them support to define it.