Question 107

A risk manager assessed all project risks, and the team is now identifying common groupings of risks. What tool or technique is used to perform this risk assessment?

    Correct Answer: A

    To identify common groupings of risks after having assessed all project risks, the appropriate tool or technique is the Risk Breakdown Structure (RBS). The RBS is a hierarchical representation of risks organized by their categories, which helps in grouping similar risks together. This aids in understanding and managing the risks more effectively at a project level.

Discussion
yandasatriaOption: A

the answer should be A. Risk have been identified, then we should make a category of risk, mean RBS the correct method

MikeMarloOption: A

RBS is a tool & Technique is not an input. Do not mistake with WBS, that indeed it is an input/output. RBS = hierarchical representation of risks according to their categories. They are in the first stages of categorization > risk group identification

3d83ab7Option: B

The question is asking what tool or technique was used. Now options A, C and D are inputs they are not tools or techniques. the only tool or technique here is B .

AzharmakOption: A

Common Grouping has to be RBS. So its A

AhmedRashadOption: A

Correct Answer: A