Question 122

A project manager has finished the project charter for a project and has now moved into the planning phase. In the first planning meeting, the project manager is trying to determine the risk tolerance and risk attitudes of the project’s key stakeholders.

What is the first resource the project manager should reference?

    Correct Answer: C

    When trying to determine the risk tolerance and risk attitudes of the project's key stakeholders, the first resource a project manager should reference is the Enterprise Environmental Factors (EEFs). EEFs encompass internal and external environmental factors that can influence the project's success, including the risk tolerance and attitudes of stakeholders. These factors provide foundational insights into the organization’s culture, structure, and risk appetite, making them the most appropriate initial reference for assessing stakeholder risk attitudes.

Discussion
emikhaelOption: C

should be EEF

SABAJANANADAOption: C

C EEF is the correct answer

SABAJANANADAOption: C

Answer should be EEF

MikeMarloOption: B

EEF does not determine the risk attitude of the Stakeholders. It can determine some details about the external and internal factors, but not what the stakeholders think. Neither the Requirements nor the Benefits plans. Project Charter is the only document that can contain something about it. Stakeholder first analysis in Stakeholder Identification is the best choice, but it is not an option for this question.

sholgamiOption: B

STAKEHOLDERS ANALYSIS DURING THE INITIATION PHASE AND CAPTURED STAKEHOLDERS ATTITUDES AND TOLERANCE