PMP Exam - Question 1416


Due to unforeseen circumstances, a contractor was unable to mobilize the project team, which was necessary to conduct face-to-face meetings and discussions. Virtual meetings were subsequently put in place, but the local project team and end users now face a communication gap that is causing the team's low performance.

What should the project manager do?

Show Answer
Correct Answer:

Discussion

5 comments
Sign in to comment
Kim222Option: C
Aug 11, 2024

I solved all the problems. 20240812

MonBoujOption: C
Oct 19, 2024

C. Reassess continually to remove blockers for the team option C is the best choice because it allows the project manager to take a proactive and flexible approach to removing blockers and improving communication, leading to better team performance without unnecessary disruptions

prokat_mashin_na_vicecity
Sep 29, 2024

I also think answer is C, cuz its unforeseen circumstances

victory108Option: C
Oct 14, 2024

C. Reassess continually to remove blockers for the team

Ngho
Nov 14, 2024

Just passed my PMP. Thank you Examtopics and to all the contributors as well!

Suldan
Apr 27, 2025

Congratulations Ngho, how similar were the questions in this site with the actual PMP?