Question 72

You are the program manager for your organization and you're coaching Tom, an aspiring program manager, on program management. Tom is curious about controlling communications. Which one of the following is an output of the communications control process?

    Correct Answer: D

    Performance reports are a key output of the communications control process. These reports provide critical information on how the program is performing across various metrics such as scope, schedule, cost, quality, and risk. They help in keeping stakeholders informed about the program's progress and performance, making them essential for effective communication management.

Discussion
SammyrOption: D

D : performance reports

ReevesT

Figure 10-7, 6th edition 10.3 Monitor Communication Outputs: Work Performance Information Change Requests PMP updates to Commucation Mgmt Plan and Stakeholder Engagement Plan Document Updates

[Removed]Option: D

D. Performance Reports. Performance reports are a key output of the communications control process. These reports provide information on how the program is performing in various areas such as scope, schedule, cost, quality, and risk. They are essential for keeping stakeholders informed about the program's progress and performance. These reports often include status updates, progress measurements, and forecasts, which are crucial for effective communication management in a program.