Question 110

You are a program manager of a program. You are required to compile performance data of your program. These data will be sent to relevant stakeholders. You are reviewing the status reports of all projects including the costs, schedule, scope, risks, and other performance data.

In which of the following processes are you working on?

    Correct Answer: D

    The process you are working on is 'Monitor and Control Program Performance'. This process involves continuously tracking, reviewing, and regulating the progress of the program to meet the performance objectives defined in the program management plan. It includes comparing actual performance with planned performance, analyzing variances, assessing trends, and implementing changes when necessary. Reviewing status reports, including costs, schedule, scope, risks, and other performance data, aligns with the activities performed during the monitoring and controlling efforts to ensure the program's objectives are met.

Discussion
happykaurOption: D

Remaining are not processes as per PGMP

tungdtOption: D

D is correct Report Program Performance for Program Close

hanyulinOption: D

D is the right answer for spm V4.

hanyulinOption: A

A is the right answer for spm V4.

hanyulin

Sorry answer D.

[Removed]Option: C

C. Report Program Performance. The Report Program Performance process involves collecting, analyzing, and distributing performance information about the program. This includes status reports, progress measurements, and forecasts, which are then communicated to stakeholders. The goal of this process is to provide stakeholders with information regarding how well the program is performing against its planned objectives and any areas where corrective action might be needed.