Question 259

An agile team is working on a 2-week sprint to deliver business value. About 1 week after the sprint starts, the team members do not feel confident about the product increment they are building. They do not want to wait until the end of the sprint and want to validate the product increment with the product owner now.

What should the project manager do to mitigate this risk?

    Correct Answer: B

    To mitigate the risk of the team not feeling confident about the product increment they are building, it is important to address this concern promptly. Scheduling an additional interim demo with the product owner allows for early feedback and validation. This ensures that any misalignments or issues can be identified and corrected before investing further effort into the product increment, thereby helping the team maintain alignment with the product owner's expectations and potentially preventing wasted effort. This approach aligns with agile principles of iterative development and continuous feedback.

Discussion
Adeshola1960Option: B

B. Schedule an additional interim demo with the product owner. To mitigate the risk of the team not feeling confident about the product increment, the project manager should schedule an additional interim demo with the product owner. This will give the team an opportunity to validate their work with the product owner and receive feedback early in the sprint. This feedback can then be incorporated into the work before the end of the sprint, which can improve the quality of the product increment and increase the team's confidence in it. Additionally, it's important for the project manager to communicate the need for an additional demo with the stakeholders and to make sure that the team has enough time to incorporate the feedback into their work.

JMCCRAYOption: B

B. Schedule an additional interim demo with the product owner. In Agile methodologies, frequent feedback loops are crucial to building high-quality products. In this scenario, the team members have recognized a risk and want to validate the product increment with the product owner before the end of the sprint. Therefore, the project manager should schedule an additional interim demo with the product owner to provide feedback and ensure that the team is on the right track. This will help the team identify any gaps or misunderstandings early on and make any necessary adjustments, reducing the risk of delivering a product that does not meet the product owner's requirements.

MuntadherOption: C

Going with C because you cant stop sprint in the middle. + u need to wait iteration finished after that review with product owner. so C as this concern will be addressed in the retrospective.. as this is Agile not Predective. if predective will be B.

ParamakOption: B

In this scenario, the team is seeking feedback to ensure they are on the right track, which is a proactive approach to mitigating risk. The best option to address this need is to facilitate communication and collaboration between the team and the product owner without disrupting the sprint schedule. Therefore, the most appropriate action is: B. Schedule an additional interim demo with the product owner.

mdkhassanOption: B

An agile project can have an interim demo in the middle of the sprint. In fact, it is common practice in agile methodologies to have regular demonstrations or showcases of the work completed during the sprint. These demos provide an opportunity for the team to present their progress to stakeholders, including the product owner, and gather feedback. By having an interim demo in the middle of the sprint, the team can validate their work, ensure alignment with the product owner's expectations, and make any necessary adjustments or course corrections early on.

josephsafiranOption: B

The project manager should choose option B. Schedule an additional interim demo with the product owner. In Agile methodologies, feedback and adaptation are key principles. If the team members are not confident about the product increment they are building, it’s important to address this concern as soon as possible. Scheduling an additional interim demo with the product owner allows the team to validate their work and receive necessary feedback, which can help them adjust their approach if needed and continue delivering value.

Bruce_LiuOption: B

Obvoiously B, C is not wrong but not efficient. ddressing the issue in the retrospective (Option C) is important but doesn't provide a timely solution for the immediate concern of product validation.

DeeskiOption: C

Iteration retrospective is where the team decides if they are going to continue, stop, or start an action to improve both the process and product. A retrospective is a regular occurring workshop in which participants explore their work and results in order to improve both process and product. Retrospectives are a form of lessons learned meeting.

ChezQWOption: C

If extending the sprint is not an option because you can't stop a sprint, then doing a demo cannot be an option either because the sprint stops to demo. That's the only reason why I see C as the answer.

Lucky_CindyOption: C

Choose C

Lucky_CindyOption: C

I agree with c

Only12goOption: B

B. Schedule an additional interim demo with the product owner. Explanation: If the team is unsure about the direction they are heading with the product increment, it is essential to get early feedback from the product owner to ensure they are aligned with the expected outcome. Waiting until the end of the sprint might result in wasted effort if the increment is not what the product owner expected. An interim demo allows for early validation and course correction if necessary.

bu02951Option: C

I think C is the better choice. because the sprint just passed 1 week, I don't think we can demo anything from here, Can that team member demo anything?

TuanitOption: B

schedule an interim demo with PO

zayn_1983Option: C

C. Interim sprint Demo is not part of scrum event, every event has timebox

Fyrus

they are not saying they are using Scrum, even if we had scrum elements. There's nothing wrong with having feedback earlier from the PO. Still, we can't stop the sprint or change it's timebox since it will not be productive Tailoring is the key here. Something that I don't like about the scrum guide is that it is strict, it's like "if you are not following exactly what we are saying you are not using scrum". So be it. I'll do whatever better fits my reality

victory108Option: B

B. Schedule an additional interim demo with the product owner

AbbasTakiOption: B

B. Schedule an additional interim demo with the product owner.