Exam PMP All QuestionsBrowse all questions from this exam
Question 369

After the project charter's approval, the project manager needs to work on detailed project requirements, constraints, and assumptions with stakeholders.

However, not all of the stakeholders are immediately available for a meeting in the short term.

What should the project manager do in order to gather the information needed from stakeholders?

    Correct Answer: B

    After the project charter is approved, it is essential to gather detailed project requirements, constraints, and assumptions from all stakeholders to ensure an accurate and complete project management plan. If not all stakeholders are immediately available for a single meeting, the best approach is to reach out to them individually via email, phone calls, or separate meetings. This method ensures that every stakeholder's input is considered, facilitating a comprehensive and well-informed planning process.

Discussion
Hung3102Option: B

B. Email, call, or meet with each stakeholder separately to obtain their input. Since not all stakeholders are available for a meeting, the project manager should reach out to them individually to gather the necessary information. This could be done through emails, phone calls, or individual meetings. It is important to ensure that all stakeholders have an opportunity to provide input to ensure that the requirements, constraints, and assumptions are properly identified and documented.

Hung1

Option D, meeting with the project management team to build the project management plan before consulting stakeholders, may not be the best solution as it is important to gather input from stakeholders before building the project management plan, to ensure that the plan is based on accurate and complete information.

KesavaperumalOption: D

I thought D is right answer

TBT_1Option: B

D cannot be correct, how can you create the project management plan without the stakeholder analysis?

YuunsOption: B

D does not achieve what is asked by the question.

TrytrioOption: D

D should be right

aqz_111

Based on the question, it is required to get stakeholders' engagement for the project. it is required to understand the stakeholders' current engagement status and develop a strategies accordingly. it is also the next step after the project Charter was approved. Therefore, i select D

tonybuivannghiaOption: B

In this situation, we are in identifying stakeholders and not form the team, so D is incorrect.

Lucky_CindyOption: B

B. Email, call, or meet with each stakeholder separately to obtain their input

David983Option: B

The PMP can´t be performend without considering the requirements, constraints, and assumptions related to all the stakeholders, so D can´t be correct. B. Email, call, or meet with each stakeholder separately to obtain their input

victory108Option: B

B. Email, call, or meet with each stakeholder separately to obtain their input

AsakthiOption: D

D. Meet with the project management team to build the project management plan before consulting stakeholders

uzeemakiOption: B

B. From the PMP process chart, you identify stakeholders after the project charter is developed.

RayhohoOption: B

B is the answer. PM should reach out stakeholders if possible actively.

ktwin1973Option: B

B. Email, call, or meet with each stakeholder separately to obtain their input. In this situation, the project manager should reach out to each stakeholder separately to obtain their input on the detailed project requirements, constraints, and assumptions. This approach allows the project manager to gather the information needed while accommodating the availability of each stakeholder. Holding a meeting with only the available stakeholders (option A) may not capture all necessary input and could lead to gaps in the requirements. Escalating to the project sponsor (option C) is not necessary at this stage, and meeting with the project management team before consulting stakeholders (option D) could delay the project unnecessarily.