PMP Exam - Question 801


In a project progress review meeting, the end user raises concern about the quality of the construction of the project. What should the project manager do next?

Show Answer
Correct Answer: B

When concerns about the quality of the construction are raised, the project manager should first refer to the requirements document. This document contains the agreed-upon specifications and criteria for the project. By reviewing it, the project manager can determine if the construction meets the specified requirements and quality standards, and identify any discrepancies. This step is essential in addressing quality issues effectively, ensuring the project aligns with the stakeholders' expectations and the original plan.

Discussion

15 comments
Sign in to comment
xcjxcjOption: B
Jul 18, 2024

A. Quality = technical ? B. Wrong requirement or i understand different? C. Risk related ? D. Quality checklist B. and D. are relevant, B sounds better as question is what to do next

AbdelmonmOption: B
Aug 2, 2024

The project manager should refer to the requirements document (Option B). This will help in understanding the agreed-upon specifications and criteria for the construction project. By referring to the requirements document, the project manager can assess whether the concerns raised by the end user align with the specified requirements. This step is crucial in addressing quality issues and ensuring that the project meets the expectations outlined in the requirements. It provides a basis for evaluating the current state of the project and identifying any deviations from the agreed-upon standards.

khaleghiOption: A
Feb 29, 2024

A. Request a special technical meeting.

Remmy12Option: D
Mar 16, 2024

Checklist is one of the quality control measurement

adingmaki
Apr 10, 2024

When you plan, you also immediately build quality in the requirements. It's B. Implementation checklist, haven't heard. Although there is a checklist in quality.

Only12goOption: B
Apr 23, 2024

B then A if need be: While calling a special technical meeting (Option A) could be a valid action in some cases, the initial response to the end user's concerns about the quality of construction would typically involve referencing the requirements document (Option B). The reason for this is that the requirements document serves as a critical reference point to determine whether the construction aligns with the specified requirements and quality standards. It provides a basis for evaluating the quality of the work and identifying any discrepancies. If, after referencing the requirements document, it becomes clear that there are issues or uncertainties that require a more detailed technical discussion, then convening a special technical meeting (Option A) may be the appropriate next step.

victory108Option: B
Apr 9, 2024

B. Refer to the requirements document

Joelush
Apr 11, 2024

D for me

slick90Option: B
Apr 17, 2024

The only answer is B, that is how you check what was agreed upon.

odylecOption: B
Jun 25, 2024

B is the answer

AbdelmonmOption: A
Jul 16, 2024

When concerns about the quality of construction are raised by the end user, it's important to delve into the specifics and address the issue in a focused manner. Requesting a special technical meeting allows for a more detailed discussion involving relevant technical experts and stakeholders. This meeting can help identify the root cause of the quality concern, assess the current status of construction against project requirements, and formulate a plan for corrective actions if needed. It provides a forum for in-depth technical discussions and ensures that the concerns are thoroughly investigated and addressed.

Victory007Option: A
Jul 17, 2024

This meeting would involve the project team and relevant stakeholders to discuss the quality concerns raised by the end user. It’s important to address these concerns promptly and effectively to ensure the project meets the required standards and expectations. The meeting would provide an opportunity to understand the specific issues, assess their impact, and develop an appropriate action plan

kevzzzOption: B
Jul 17, 2024

Requirements documentation describes the business solution for a particular project, including the user's expectations and needs, the purpose behind that solution, and any high-level constraints that can affect successful deployment. It typically serves as the guideline for stakeholders to decide on project priorities, structure, and design to guarantee the project stays aligned with the business's overall goals.

androloginOption: D
Mar 18, 2025

Check implementation details for any possible missteps

AnssooOption: D
Apr 27, 2025

Answer is D. To PMP EXPERTs who select B, Don`t mixup your personal opinion.