During what process should a project manager assign a risk owner?
During what process should a project manager assign a risk owner?
The correct answer is during the 'Plan Risk Responses' process. This is when specific actions to address each identified risk are determined, and responsibilities, including assigning a risk owner, are clearly defined. In the 'Plan Risk Responses' process, you've already identified the risks through earlier steps, and now it's essential to allocate owners who will be responsible for implementing the agreed-upon risk responses.
Risk owner first assigned when we identify risks. Identifying Risk is part of Paln Risk Managment
D. Identify Risks
D is the right answer in all circumstances except validation of the risk owner scenario
D is the right answer during risk identification not the plan
In Identify Risks, you should look for potential risk owners. However, in Plan Risk Responses, you ALLOCATE risk owners to every risk you have.
The question does not say "Possible risk owner" which only happens in Identofy risks therefore the answer is A
A preliminary risk owner maybe nominated at the end of the "Identify Risk" process and should be confirmed during the " Qualitative Risk Analysis" process. During the "Plan Risk Response" process, the role of the already nominated risk owner is to develop the response plans. In my opinion, the best answer should be " Qualitative Risk Analysis" and since it's not listed then second best answer would be "Identify Risks".
The Answer is D. Identify Risks Key Success Factors in RMP BOOK
Ans: D Reference: Page 32 Last para of "The Standard for Risk Management".
D is the correct answer
D Identify risks. The risk owner will be part of identifying the responses.
Risk owner is always assigned after risks have been identified. So the answer has to be Plan Risk Responses or A
D. Identify Risks
In Plan Risk Management there is not risk oener atribution.