Question 1216

While managing a project using a hybrid approach, the project manager realizes that there is a high level of rework due to quality issues. Because of that, each feature is taking longer than initially estimated.

What should the project manager do to address the issue?

    Correct Answer: A

    To address the quality issues and the resulting rework in a hybrid project approach, the project manager should leverage agile practices, which include addressing concerns during the sprint planning meeting. This provides an opportunity for the team to discuss and identify the root causes of quality problems, collaboratively develop solutions, and implement changes to improve processes and enhance deliverable quality more effectively. This iterative improvement fits well within the agile methodology, promoting continuous improvement and adaptability.

Discussion
UppersquareCapitalOption: A

A. Address the issue during the next sprint planning meeting. This approach aligns well with agile practices. During the sprint planning meeting, the team can discuss the quality issues, identify the root causes, and agree on strategies to improve quality and reduce rework. This may include implementing stricter quality control measures, enhancing testing protocols, or providing additional training. Addressing the issue within the agile framework can help the team quickly adapt and improve their processes.