Question 135

The project manager is reviewing the lessons learned from a previous similar project. The previous project was delayed due to the delay in delivery of a gas turbine generator (GTG). Construction of the previous project had to be shut down unexpectedly to wait for the late delivery of the GTG.

What should the project manager do first?

    Correct Answer: C

    The project manager should include the risk in the register and communicate with the stakeholders. This helps in formally acknowledging the risk, assessing its impact, and planning appropriate mitigations. Immediate communication with stakeholders ensures that everyone is aware and can contribute to planning and risk response strategies. This proactive approach is essential for effective risk management.

Discussion
MikeMarloOption: C

You know a possible risk, you put it in the Risk Register with all its data.

aws_guru1Option: C

I will go with C as the correct answer.

SABAJANANADAOption: C

C should be the correct answer,