PMP Exam QuestionsBrowse all questions from this exam

PMP Exam - Question 835


A member of the board of directors has asked the project manager for the estimated cost of the minimum viable product (MVP). The estimated cost is needed in order to get formal approval for this project.

How should the project manager report this cost?

Show Answer
Correct Answer: B

To provide the estimated cost of the minimum viable product (MVP) for formal approval, the project manager should determine the control accounts and use a top-bottom estimate. This approach is practical for the initial stages of strategic decision-making when detailed information about the project deliverables and their costs might not be fully available. By using control accounts, which are higher-level work packages, the project manager can create a more accurate and detailed estimation of the MVP's costs before the project is approved.

Discussion

16 comments
Sign in to comment
MHONKOption: C
Sep 3, 2023

C. Estimate user story points and forecast a budget for that deliverable. The requirement is MVP and it is agile.

mmhawish
Feb 11, 2024

It was not mentioned in the question that it is an Agile project

sudersonfernando
Oct 1, 2023

Estimate to Completion is required so I would go with option A.

adingmaki
Oct 10, 2023

C. I think

adingmaki
Oct 10, 2023

https://www.youtube.com/watch?v=i1GA40fE3cA

victory108Option: C
Oct 11, 2023

C. Estimate user story points and forecast a budget for that deliverable

Only12goOption: C
Oct 23, 2023

Based on the phrasing "How should the project manager report this cost?", the most fitting answer would be C. "Estimate user story points and forecast a budget for that deliverable." Estimating user story points and forecasting a budget based on those estimates is a direct method for determining the cost of a deliverable like an MVP, especially in agile environments where user stories are utilized. This approach provides a clear and specific report on the estimated cost for the MVP.

ChezQW
Oct 24, 2023

Why not B seeing that the project has not started and the budget is needed to approve the project. There should not be any completed work or user stories so why not use a top-bottom estimate?

sk8chick68
Nov 4, 2023

Answer should be B. Determine the control accounts and use a top-bottom estimate. Cannot be A because the project does not have approval yet, there is no earned value yet. . The Top-down approach is practical for the initial stage of strategic decision-making and in situations where the information required to develop accurate duration and costs estimates is not available in the initial phase of the project. Hence, top-down estimates are used initially until the tasks in WBS are defined clearly, which enable the development of well-defined schedules and budget.

cb4a6c4Option: B
Dec 9, 2023

Breaking MVP will help arriving at a cost which would be a focused analysis. Since the project is not yet started D can not be true and same applies to C as it might not give a clear picture on MVP cost estimate.

cb4a6c4
Dec 26, 2023

Change of mind. It is option C. While traditional top-down estimating techniques may have limitations in an agile context, option C reflects the agile mindset of breaking down work into user stories and estimating effort for each, contributing to the overall budget estimation for the MVP.

odylecOption: C
Dec 26, 2023

C is the answer

UppersquareCapitalOption: B
Jan 11, 2024

B. Determine the control accounts and use a top-bottom estimate. In order to provide the estimated cost of the minimum viable product (MVP) for formal approval, the project manager should use a top-down estimate. This involves breaking down the project into control accounts (major work packages or deliverables) and providing cost estimates for each control account. This approach allows for a more detailed and accurate estimation of costs related to the MVP. Option C suggests estimating user story points, which is more related to Agile methodologies but may not be directly applicable to a traditional project.

chlaithemOption: C
Jan 12, 2024

This option leverages the flexibility and agility of Agile methodologies, which are often used for developing MVPs. By taking these steps: Estimate user story points: By considering the functionalities and features planned for the MVP, assign appropriate point values reflecting their complexity and effort. Forecast a budget: Based on the estimated user story points and the team's historical data (e.g., average cost per point), develop a realistic budget forecast for the MVP development.

kevzzzOption: B
Jan 17, 2024

The Top-down approach is practical for the initial stage of strategic decision-making and in situations where the information required to develop accurate duration and costs estimates is not available in the initial phase of the project. Hence, top-down estimates are used initially until the tasks in WBS are defined clearly, which enable the development of well-defined schedules and budget. When are user stories written? User stories are written throughout the agile project. Usually a story-writing workshop is held near the start of the agile project.

AbdelmonmOption: C
Jan 20, 2024

In Agile and Scrum methodologies, estimating the cost for a project is often done based on user story points. User story points are a relative measure used to estimate the size or complexity of individual user stories. The project manager can estimate the cost of the minimum viable product (MVP) by assigning story points to the user stories, and then using historical data or team velocity to forecast the budget for that deliverable. This approach aligns with Agile principles and provides a flexible way to estimate and plan based on the features or user stories that will contribute to the MVP.

mmhawish
Feb 11, 2024

It was not mentioned in the question that it is an Agile project

dinodragon
Jun 16, 2024

Without project approval .. no epics or users stories would be available. I do not think answer would be C

buvana
Mar 20, 2024

B. Determine the control accounts and use a top-bottom estimate.

AnssooOption: A
Apr 27, 2025

A, In MVP, BAC is being used.