The project manager wants risk metrics established for the new project. Which of the following metrics listed is best suited for this purpose?
The project manager wants risk metrics established for the new project. Which of the following metrics listed is best suited for this purpose?
Effectiveness of response plans is the best metric for establishing risk metrics in a new project. This metric directly measures how well the project team is managing and mitigating risks through planned responses, which is critical to maintaining project stability and success. The number of defects identified, while useful, does not directly correlate to the effectiveness of risk management.
D is the answer