PMP Exam QuestionsBrowse all questions from this exam

PMP Exam - Question 542


A project manager is in rapid development mode on a joint application development module. The company wants delivery to occur in two weeks. The module needs to be integrated with other modules on a similar timeline, but release management has a three-week backlog.

What should the project manager do?

Show Answer
Correct Answer: B

The project manager should speak to the stakeholders to resolve the bottleneck and see how the entire process can be streamlined. This approach addresses the core issue of the release management backlog and seeks a sustainable solution that aligns both the development and integration timelines without overburdening the team or causing delays.

Discussion

3 comments
Sign in to comment
JamrockOption: B
Aug 20, 2023

other answers were so bad that this was the logical solution :)

victory108Option: B
Sep 3, 2023

B. Speak to the stakeholders to resolve the bottleneck and see how the entire process can be streamlined

DavidTriOption: B
Jul 10, 2024

Not A - because PM should not push member deliver quick & more Not C - cannot tighter deadline Not D - should not slow team to align with release date