Question 275

Due to organizational changes, a new product owner joins a project. The product owner wants to review the process used to obtain team members, facilities, equipment, materials, supplies, and other resources necessary to complete project work.

What process should the project manager review with the product owner?

    Correct Answer: A

    The process that the product manager should review with the product owner is 'Acquire Resources.' This process is explicitly about obtaining team members, facilities, equipment, materials, supplies, and other resources necessary to complete project work. It is part of the Project Resource Management knowledge area, focusing on identifying, acquiring, and managing the resources needed for project activities. Reviewing this process ensures that the project team has the necessary resources to deliver the project successfully.

Discussion
Andrew_1980Option: B

Reviewing the plan created earlier

shubu2276Option: B

In this scenario, since the new product owner wants to review the process related to obtaining resources, the project manager should review the "Plan Resource Management" process with the product owner.

HPouriaOption: A

The Acquire Resources process is part of the Project Resource Management knowledge area, and it focuses on obtaining the resources required to complete the project work. This process involves identifying, acquiring, and managing the resources needed for project activities. Reviewing this process with the new product owner can help ensure that the project team has the necessary resources to deliver the project successfully.

jesslhongOption: A

I would think A is the more specific/appropriate answer