A program manager is identifying and verifying risks as outlined in the risk management plan.
The results will be recorded in which of the following?
A program manager is identifying and verifying risks as outlined in the risk management plan.
The results will be recorded in which of the following?
The results of identifying and verifying risks as outlined in the risk management plan are recorded in the risk register. The risk register is a document that contains details about each identified risk, including its characteristics, risk responses, and status.
A is correct