A program manager is identifying and verifying risks as outlined in the risk management plan.

The results will be recorded in which of the following?

Show Answer
Correct Answer: A

The results of identifying and verifying risks as outlined in the risk management plan are recorded in the risk register. The risk register is a document that contains details about each identified risk, including its characteristics, risk responses, and status.