Question 337

A customer reviewed the plan for a project with high uncertainty. The customer expressed concerned about the work requiring so many iterations with a risk of not reaching the mandatory delivery date.

Which approach should the project manager use in this situation?

    Correct Answer: C

    In a situation with high uncertainty and a mandatory delivery date, the project manager should use a hybrid approach. This combines the flexibility and iterative benefits of Agile methodologies with the structured planning and risk management of predictive approaches. The hybrid approach allows the project manager to address uncertainties and adapt to changes while ensuring that there is a clear plan to meet the fixed deadline.

Discussion
AlphashamOption: C

I believe it should be C since the customer is requiring a hard stop for the project.

IliaSXOption: C

I think it's C, as there is a deadline.

ChezQWOption: D

In the agile approach time and costs are fixed with a variable scope. This is preferred when the requirements are not clearly defined. I understand that the PM is worried about the number of iterations, however the agile team should be able to address this because they are self-organizing.

Bruce_LiuOption: C

Customer is concerning both delivery date and too many iterations. Need a balanced approach.

AesamOption: D

In Agile tringle, Schedule and cost are fixed and scope is variable, so in order to meet the mandatory date with uncertainty, agile will be a suitable option.

ardas91Option: D

Uncertainty means either Iterative or Incremental (Adaptive). Hybrid cannot be it here since there is no chance of being Predictive for any of the part of the project. This Cannot be Kanban since there is a deadline. Hence the option is only left as Agile.

OruMaryOption: D

D. there is too much uncertainty, so it eliminates any option of a predictive.

josephsafiranOption: C

The project manager should use C. Hybrid approach. This approach combines elements of both predictive (or traditional) and Agile methodologies. It allows for flexibility in areas of high uncertainty (where Agile shines) while maintaining a level of predictability for certain aspects of the project (where traditional methods are beneficial). This can help manage the customer’s concerns about the risk of not reaching the mandatory delivery date due to numerous iterations.

mesacgonOption: C

Debería ser C. ya que tiene una fecha obligatoria y es de alto riesgo, eso decribe la parte predictiva y como esta en iteraciones eso describe la parte ágil.

Only12goOption: C

In a situation where a customer is concerned about a project with high uncertainty and the risk of not reaching the mandatory delivery date, the project manager should consider using a hybrid approach. A hybrid approach combines elements of both predictive (traditional) and agile methodologies to tailor the project management approach to the specific needs and characteristics of the project. This allows for flexibility in addressing uncertainty and adjusting the project's approach as needed while still providing some level of predictability and structure.

kevzzzOption: C

Just because the term Hybrid, Agile and deadlines are used, it doesn't mean that Hybrid is just Agile and Waterfall. Hybrid is the best use case and needs for that project, mix and match, etc. Because team members will create, test, and revise iterations until they get to a satisfying solution, the iterative timeline isn’t clearly defined. Hybrid project management is a versatile approach that combines elements from different project management frameworks, allowing you to tailor your methodology to best suit the project at hand. By merging various methods, organizations can capitalize on the strengths of each approach while mitigating their weaknesses.

AcmkOption: C

Hybrid since deadline is given

zayn_1983Option: C

c. By using a hybrid approach, the project manager can maintain the flexibility and adaptability of Agile methodologies to address the uncertainty and changes that arise during the project. At the same time, the project manager can incorporate predictive planning and controls to provide more visibility and predictability for meeting the mandatory delivery date. This can help manage stakeholder concerns about project progress and ensure alignment with customer expectations.

victory108Option: C

C. Hybrid approach

aishOption: C

The project manager could apply Agile principles for managing uncertainty and iterative development while also incorporating certain predictive planning aspects to ensure the project stays on track to meet the mandatory delivery date.

Dawn6699Option: C

In situations with high uncertainty and risk of not meeting the mandatory delivery date, it would be best for the project manager to use a Hybrid approach. This approach combines the predictability of a predictive approach with the adaptability and flexibility of an agile approach. The Hybrid approach would allow the project manager to have a clear understanding of the project scope, timeline, and budget from the beginning (predictive) while also allowing for adjustments and changes to the project as more information becomes available (agile). This would help to minimize the number of iterations required while still keeping the project on track to deliver within the required timeline. From chartGPT

ktwin1973Option: C

Answer C, Hybrid approach, could also be a valid option in this situation. A hybrid approach combines elements of both predictive and adaptive approaches and can be tailored to meet the specific needs of the project. In this case, the project manager could use a hybrid approach that allows for some level of predictability and planning while also incorporating adaptive elements to address the high uncertainty and potential for multiple iterations.