Exam PMP All QuestionsBrowse all questions from this exam
Question 519

A technical manager newly appointed by the client, visits the project site to verify the project deliverables. The technical manager feels that the project manager has not been providing enough information.

What should the project manager do first to resolve this situation?

    Correct Answer: D

    When a new stakeholder, such as a technical manager, expresses concerns about the sufficiency of project information, the project manager should first revisit and update the stakeholder engagement plan. This plan outlines strategies and actions for effectively engaging stakeholders throughout the project's lifecycle. By updating this plan, the project manager ensures the stakeholder's needs and expectations are addressed, which can resolve the issue of insufficient information provision.

Discussion
victory108Option: B

B. Identify the lack of information as a risk and update the risk register

PMPStudent

Review the engagement plan to see if he is even included in the stakeholder register, and if he is already there, the PM needs to reassess this new stakeholder needs. All of this is done through stakeholder engagement.

MoumitaOption: D

updating the Stakeholder Engagement Plan is first steps, then schedule meetings with technical manager as a next step

PMPStudentOption: D

D is correct. The question talks about "project manager has not been providing enough information". Which means, the PM needs to review the stakeholder engagement plan. The next best option would have been to review and update the communication plan, which is not provided in the options above.

DavidTriOption: D

voted D, because PM need to define the engagement plan before do the action such as schedule meeting frequentcy

Fiona1212Option: D

D. Review and update the stakeholder engagement plan

JYKL88Option: D

D is good for this

Hung3102Option: D

D is ans

YSO34Option: D

why update the stakeholder engagement plan ? the engagement did not change.

rajeshtk

B seems to be correct. Stakeholder engagement plan doesn't give project information

SuHo2610

I would go with D, as the technical manager was "newly appointed" - so probably he/she was missed in the communications, as he/she was not in the stakeholder engagement plan.