What are the three components of a work breakdown structure (WBS) dictionary? (Choose three.)
What are the three components of a work breakdown structure (WBS) dictionary? (Choose three.)
A work breakdown structure (WBS) dictionary typically includes a list of resources, a description of work, and acceptance criteria. The list of resources specifies the resources required to complete each task. The description of work provides detailed information about the work to be performed. Acceptance criteria outline the conditions that must be met for the work to be accepted. These three components are essential for detailed project planning and execution.
I think it should be B, D, E. List of resources (C) is managed separately from the WBS dictionary, while Description of risks (B) helps in identifying potential threats to the project's success and planning appropriate risk responses.