A project manager has been managing a highly complex project. The project manager has ensured that all of the required tasks have been completed. During a recent external audit. The project manager was informed of a heavy penalty being levied on the project for the latest module that was implemented.

What should the project manager have done to ensure that there were no liabilities arising from the recent implementation?

Show Answer
Correct Answer: D

To ensure that there are no liabilities arising from an implementation, the project manager should have followed and received all required approvals as per the organizational procedures. This would have included verifying that every necessary aspect of the project, including compliance and quality checks, was formally approved to prevent any oversight that could lead to penalties or non-compliance issues.

Discussion

4 comments
Sign in to comment
Solid_JehutyOption: A
Mar 31, 2023

I feel like the answer is A. Can anyone explain?

cyberf
May 26, 2023

I thought it was A as well but it mentioned the deliverable has been completed but not approved. The deliverable must be approved by the product owner before it is released

SteAleOption: D
Jul 25, 2023

https://www.examtopics.com/discussions/pmi/view/57332-exam-pmp-topic-1-question-3410-discussion/

victory108Option: D
Sep 22, 2023

D. Ensured that all the required approvals were received per the organizational procedures

DavidTriOption: D
Jul 11, 2024

The question is not clearly but for make sure all package & document is follow correctly, PM need follow & get approval from organization procedure