Exam PMP All QuestionsBrowse all questions from this exam
Question 1175

A project manager just finished a meeting to identify the main stakeholders of the project. What should the project manager do next?

    Correct Answer: A

    After identifying the main stakeholders of a project, the next step for a project manager is to analyze the stakeholders. This involves understanding their needs, expectations, influence, and potential impact on the project. This analysis helps in developing a stakeholder management plan to engage and communicate with the stakeholders effectively throughout the project lifecycle, ensuring their support and addressing any concerns they may have.

Discussion
sidjeOption: A

Selon le guide PMBOK après avoir identifier les parties prenantes, il faut les analyser.

AditechOption: A

A According to the PMBOK Guide, the project manager should document the identified stakeholders, analyze their needs, expectations, and influence on the project, and develop a stakeholder management plan to effectively engage and communicate with them throughout the project lifecycle.