Question 706

A project manager has recently been assigned to a new project. When the project manager first meets the project team, the team tells the project manager that all of the management plans and documents for the project are missing.

What should the project manager do?

    Correct Answer: D

    The project manager should create the project management plans with the project team and share the documents with the stakeholders. This approach ensures that the project has a strong foundation, incorporates input and agreement from all involved parties, and mitigates the risk of missing essential information. Collaborating with the project team in developing these documents ensures that the plans are tailored to the specific needs and context of the current project, rather than relying on potentially outdated or unsuitable templates from previous projects.

Discussion
MRichieOption: C

the answer is C, the first approach is to adapt to save time instead of creating from scratch. dont forget OPA

MRichieOption: C

the answer is C, the first approach is to adapt to save time instead of creating from scratch. dont forget OPA.

Only12goOption: D

Given the importance of having proper project management plans in place and the need for collaboration: D. Create the project management plans with the project team and share the documents with the stakeholders. This is the most comprehensive and appropriate approach, ensuring that the project has a strong foundation and that all parties are aligned.

victory108Option: D

D. Create the project management plans with the project team and share the documents with the stakeholders