A project manager has to share a status report with a new stakeholder and is trying to determine the level of detail to include in the report. Which document best details the information the project manager needs to make this decision?
A project manager has to share a status report with a new stakeholder and is trying to determine the level of detail to include in the report. Which document best details the information the project manager needs to make this decision?
The Communications Management Plan details how project communications will be planned, structured, monitored, and controlled. It includes information such as the communication requirements of stakeholders, the frequency and detail of the information to be shared, and the method of communication. Therefore, it is the best document to determine the level of detail to include in the status report for a new stakeholder.
Communications management plan
why not A
Status report
C-Communications Management Plan