CAPM Exam - Question 138


A project manager has to share a status report with a new stakeholder and is trying to determine the level of detail to include in the report. Which document best details the information the project manager needs to make this decision?

Show Answer
Correct Answer: C

The Communications Management Plan details how project communications will be planned, structured, monitored, and controlled. It includes information such as the communication requirements of stakeholders, the frequency and detail of the information to be shared, and the method of communication. Therefore, it is the best document to determine the level of detail to include in the status report for a new stakeholder.

Discussion

3 comments
Sign in to comment
MoonManBlueOption: C
Sep 24, 2020

C-Communications Management Plan

QeyamuddinOption: A
Nov 8, 2023

why not A

Cyberpleb
Jul 20, 2024

Status report

ASCAPMOption: C
Nov 21, 2023

Communications management plan