PMP Exam QuestionsBrowse all questions from this exam

PMP Exam - Question 602


A Scrum team has committed to delivering a specific capability in their first release. Multiple operational issues have prevented the developer from delivering key capabilities. The technical lead has also given notice that they are resigning from the company.

What should the project manager have the Scrum team do to recover from these issues?

Show Answer
Correct Answer: A

When faced with multiple operational issues and a key team member resigning, the project manager should have the Scrum team review constraints in the ongoing sprint planning and evaluate options for the release plan. This approach allows the team to address immediate constraints and adapt their plans to ensure the highest priority work is still delivered. By evaluating options for the release plan, the team can make informed decisions on how best to proceed given the current challenges, which aligns with Agile and Scrum principles of continuous improvement and adaptability.

Discussion

3 comments
Sign in to comment
victory108Option: A
Sep 23, 2023

A. Review constraints in the ongoing sprint planning and evaluate options for the release plan

22d5af5Option: A
Jan 9, 2024

Selected Answer: A

DavidTriOption: A
Jul 11, 2024

Currrent sprint is still on-going so PM need to review the sprint plan contrain to obtain appropriate solution