Exam PgMP All QuestionsBrowse all questions from this exam
Question 178

A program manager building the world's largest cruise ship is resolving the conflict between the two main sponsors who cannot agree on the number of food and beverage outlets to have onboard. What should the program manager do?

    Correct Answer: C

    When resolving a conflict between two main sponsors regarding the number of food and beverage outlets onboard a cruise ship, the most effective approach is to arrange a meeting with both sponsors and the steering committee to present the market analysis and work through the conflict. This approach ensures that all key decision-makers are involved in the discussion, allowing for a collaborative and data-driven resolution that considers the insights and concerns of both sponsors, ultimately leading to a more agreeable and well-informed decision.

Discussion
happykaurOption: C

In the situation where the program manager for building the world's largest cruise ship is dealing with a conflict between two main sponsors regarding the number of food and beverage outlets onboard, the program manager should: C. Arrange a meeting with both sponsors and the steering committee to present the market analysis and work through the conflict. This approach is collaborative and involves all the key decision-makers. By presenting the market analysis to both sponsors and the steering committee, the program manager can facilitate a data-driven discussion. This meeting provides a platform for each party to voice their opinions and concerns, and for the program manager to guide them towards a consensus based on market research and program objectives. This method is effective in resolving conflicts by ensuring that decisions are made with full consideration of relevant information and stakeholder inputs.

hanyulinOption: C

The answer should be C.

NawrasHamwiOption: C

I do agree with you, answer must be C

Hazem1976Option: C

Can anyone from Exam-Topics consultants justify why the answer is D? I think that the correct answer is C.

tsangcklOption: C

It is C engage sponsor and committee to resolve and design the decision. D, is not correct. Program stakeholder can be anyone and they are not the party to make decision.

tungdtOption: C

I choose C

MusfiqOption: C

Agree with happyaur's rationale for C