Question 591

During the course of a project, the project manager wants to ensure that the work carried out and the product being created do not deviate from the prescribed business value.

What should the project manager pay special attention to in order to achieve this goal?

    Correct Answer: D

    To ensure that the work carried out and the product being created align with the prescribed business value, the project manager should pay special attention to monitoring and updating the benefits realization plan. The benefits realization plan outlines how and when the project’s benefits will be delivered and measured. By consistently tracking this plan, the project manager ensures that the project remains aligned with the business objectives and value expected by stakeholders.

Discussion
SteAleOption: D

https://www.examtopics.com/discussions/pmi/view/53051-exam-pmp-topic-1-question-1847-discussion/

DavidTriOption: D

in order to archive the business value (goals) PM need to monitor benefit realizatioin plan fluently

victory108Option: D

D. Monitoring and updating the benefits realization plan